=Shift propagation does not have to occur one employee at a time.
More than one employee can be selected at a time and then all will have their shifts propagated the designated number of weeks.
To Propagate Shifts for Multiple Employees
-
Click the Schedule tab. The Schedule screen displays.
-
Click either 16 Week View or 8 Week View. The appropriate view displays.
-
Apply the Employee Schedule Selectors, as necessary, to narrow the list of employees from which to choose.
-
Click Copy shift in the Tools section. A dropdown window with all available time period choices displays.
-
Select the number of weeks to propagate the shift from the window.
-
Select the cells containing the shifts you wish to propagate.
-
Click Save. The shifts propagate, beginning with the first week after the selected cell.
Shifts do not have to be identical to be propagated at the same time. They just all need to be in the left-most column at the time of the assignment.